Renovation and Expansion 2018

Yale Nursing is proud to be working with a great team to bring you an expansion of our state-of-the art simulation lab as well as 2 new classrooms. The capital project - approximately 8,000 square feet of newly designed space in the Yale Nursing building - is fully on track to be ready for the 2018-2019 academic year. 

Read more about our simulation labs at Yale Nursing.

Highlights of the renovation include:

  • A new Primary Care Assessment lab to add to our Acute Care Assessment Lab
  • 6 new Standardized Patient rooms with an adjacent “green room” for our actors
  • A 500 square foot one-bedroom simulation apartment
     with a kitchen and bathroom
  • The addition of high-tech observation and control rooms
  • 2 new debrief rooms
  • Student and faculty workstations
  • A brand new 46-seat classroom
  • A brand new 36-seat classroom
  • An updated cafe with healthy and fresh grab-n-go offerings

We are thrilled to be working with a great team:

Architects: Svigals 
Construction: Shawmut Design and Construction
Program Management: Yale Facilities


Renovation Timeline


Date

Activity

Progress
Feb. 5, 2018 Demo begins Complete
Feb. 13, 2018 Demo kickoff reception Complete
Mar. 16, 2018 Demolition phase ends Complete
Mar. 19, 2018 Renovation phase begins On target
July 27, 2018

Significant completion

On target

Aug. 10, 2018 Estimated move-in On target
TBD, August 

Ribbon Cutting Ceremony

On target

Related News

February 13, 2018​: Yale Nursing celebrated the start of the demolition with a Renovation Kickoff Reception. Read more about the event here.